Question: Consider the following statements:
(1) The UNIT-3 of Kakrapar Atomic Power Project in Gujarat achieved its first criticality on July 22,2020.
(2) KAPP-3 is a first of a kind,indigenous 700 MW Pressurised Heavy Water Reactor(PHWR).
Of the above correct statement/s is/are:

(a) Only 1
(b) Only 2
(c) Both 1&2
(d) None of the above
Answer: (c)
Related facts:

  • The UNIT-3 of Kakrapar Atomic Power Project(KAPP-3-700 MW),located at Kakrapar,Gujarat achieved its first criticality(controlled self-sustaining nuclear fission chain reaction for the first time) on July 22,2020.
  • KAPP-3 is a first of a kind,indigenous 700 MW Pressurized Heavy Water Reactor(PHWR),thus giving a boost to the `Make in India’ initiative in the reactors sector.
  • The indigenous 700 MW PHWRS have advanced features like steel lined inner containment,Passive Decay Heat Removal System,Containment Spray system,Hydrogen management systems etc.
  • The task is achieved with the coordination and cooperation among NPCIL,Contracting Agencies,DAE units and various Central,State and local authorities.
  • The unit is the 23rd nuclear power reactor of the country.
  • KAPP-3 is the front runner in the series of sixteen indigenous 700 MW PHWRs which have been accorded administrative approval and financial sanction by the government and are at various stage of implementation.
  • NPCIL has seven more reactors,KAPP 4(700 MW),RAPP 7&8(2x700 MW),KKNPP 3&4(2x1000MW) and GHAVP 1&2(2×700 MW) under construction.
  • The fourth unit of the KAPS is likely to be commissioned by 2021.