Question : EPC package of waste-to-energy facility in Uttar Pradesh is expected to be commissioned at Ramna —
a. By September 30, 2023
b. By September 30, 2021
c. By October 20, 2021
d. None of the above
Ans. d.
Related facts —
- EPC package of waste-to-energy facility in Uttar Pradesh is expected to be commissioned at Ramna by September 30, 2022.
- For this purpose the bids commenced on June 22.
- “NTPC Vidyut Vyapar Nigam Ltd” had invited online bids on a two-stage bidding basis for the EPC (engineering-procurement-construction) package of waste-to-energy facility.
- A waste-to-energy plant with waste segregation facility of 600 tonnes per day fresh Municipal Solid Waste will be installed under the project.