Question: Ladakh recently gets Centre’s nod for transmission lines at revised cost of —
A. Rs1,310crore
B. Rs1,610crore
C. Rs1,000crore
(d) None of the above
Answer- (a)
Related facts
- Ladakh has recently (May 2021)got Centre’s nod for transmission lines at revised cost of Rs 1,310 crore.
- These transmission lines will link far-flung villages of Ladakh to the grid and phase out DG sets towards achieving carbon neutrality in the Union Territory.
- The project on completion would also provide the army and the far-flung villages with clean power round the clock.
- The DPR cost of the projects has been revised from Rs 354.74 crore to Rs 1,309.71 crore by the Central Electricity Authority.
By — Pankaj Pandey.